2015-08-03
- 04:56 Scrum Defect #1056 (Rejected): Sprint doesn't show contents and product backlog show repeated menu
- I tested scrum 10.0 on redmine 2.3.2, there are 2 issues.
1.Although I created user story with sprint, the sprint ... - I used scrum 0.7.0 on redmine 2.3.2 for nearly half a year, these days, there occur such error, it is ubnormal...when...
- 03:59 Scrum Defect #1055 (New): Internal 500 Error when going to sprint board
- Error log is here:
Rendered inline template (0.0ms)
Rendered plugins/scrum/app/views/common/_scrum_editable_v...
2015-01-26
- 11:06 Scrum Defect #847: Calendar shows 500 after install
- a question:\apps\redmine\htdocs\plugins\scrum\app\views\post_its\sprint_board\_head.html.erb
there are 2 lines:
... - 09:55 Scrum Defect #847: Calendar shows 500 after install
- 1. About translation I modified en.hml, it is fixed, but why the sprint start date and end date cannot be selected?
... - 09:26 Scrum Defect #847: Calendar shows 500 after install
- I tested 2 left issues:
I can create sprint from project setting-sprint,but now for the rename,missing translatio... - 09:14 Scrum Defect #847: Calendar shows 500 after install
- Update these plugin files:...
- 09:06 Scrum Defect #847: Calendar shows 500 after install
- a question:\apps\redmine\htdocs\plugins\scrum\app\views\post_its\sprint_board\_head.html.erb
there are 2 lines:
... - 08:04 Scrum Defect #903: start date and due date are shown as list or blank
- Please check the pitcures I attached to the issue, it is not repeated issue with #847.
- 08:04 Scrum Defect #903: start date and due date are shown as list or blank
- It is not the same defect which #847 shows, it is another bug, have you checked that? I tested, in product backlog, i...