11:57 Scrum Defect #1225: Sprint burndown chart calculated incorrectly
Hello Mr. Bartosz Firyn, how dou you manage "Epics"? Do you create User Stories as children of Epics?
I am just curi...
Vito Marolda

2018-02-20

14:58 Scrum User story #1536 (New): Add option to hide closed PBI's in Sprint Board
See example.
!example.png!
Vito Marolda

2017-12-02

18:10 Scrum Defect #1516 (New): If total of pending effort is selected and "group by" is also selected in query list, then 500 Internal Server Error
To reproduce:
# go to issues list
# add "Pending Effort" to totals
# group by priority
Vito Marolda
09:22 Scrum User story #1513 (In progress): Add Total for Pending Effort in issue query
See Example
!Immagine.png!
Vito Marolda

2017-10-05

08:55 Scrum User story #1469 (New): PBIs without tasks in Sprint board should implement spent time management in some way
The behaviour described in #1278 is very useful, but I miss spent time management when trying to use it.
This is my ...
Vito Marolda

2017-09-28

07:54 Scrum Defect #1451 (Resolved): Unable to edit User Stories with custom fields
Since latest update commit 70425e86e885ea79bc572220bde89d648d66ec58 the pop-up for editing a user story does not show... Vito Marolda

2016-05-27

15:48 Scrum Ideas for features: RE: One Sprint for multiples projects
Hello, as long as subprojects have the scrum module enabled too, you can change the project of the ToDo Items.
Our s...
Vito Marolda

2016-02-18

23:32 Scrum User story #1141 (New): Sprint estimated effort auto-fill
A simple function to fill all the days of the sprint estimated effort (for one developer) with the same value.