Forums » Problems or support »
Parent PBI status
Added by thomas mann over 7 years ago
Hi,
Relating to forum topic 358 and user story #1266, i have a question to the PBI parent staus changes to "Done" / "Solved".
In our case, tasks have nearly the same statuses like PBI items, but if i "close" / set all tasks from a PBI to "done" the PBI parent status is still showing "in progress".
(Changing a task from "new" to "in progress" is working with the PBI parent status. (PBI is changing like expected))
Could you provide any help (may i have some missconfiguration) or is this a normal / wanted behaviour?
Thanks