Sprint burndown by SPs shows the progress of the team in story points. The
valor can accurately logged by users (via pending story points field, it must
be enabled under Administration » Plugins » Scrum Redmine plugin) or with less precision when
each PBI is closed.
Logging pending SPs day by day
Every team member must log the pending SPs day by day in the PBIs. Due the
fact the plugin records every pending SPs on the day is logged, don't forget
to log that value every day if you want an accurate burndown graph.
Understanding the burndown by SPs
Pending SPs line (or lines in multi-project teams) represents the pending
SPs of Sprint PBIs day by day (this is not related in any way with the
PBI SPs field, nevertheless usually PBI pending SPs use to be equal to the
SPs field when we start working on the PBI).
Burndown on multi-project teams
If you have several projects under the Scrum team project, and you assign
PBIs & tasks to those child projects (they should also have Scrum module
enabled), then the burndown could be decomposed in several series, one serie
per subproject.