Hi all,
I have created several PBI and assigned them to one sprint. Then, I have created several tasks for one of those PBI and I have realized that those tasks appear as part of the Product Backlog. In fact, they appear duplicated within the Sprint Board: in the column of PBI (as one item itself) and in the part of the PBI/user story they belong to. Is there any way to correct it? I would like to avoid showing those tasks as PBI.
Thanks in advance.
Carlos.
Replies (4)
RE: Sprint Board showing tasks duplicated (as PBI and tasks) - Added by Emilio González Montaña about 8 years ago
Carlos, you have an error in your plugin settings.
Check the setting called Product backlog items & remove task tracker from it.
RE: Sprint Board showing tasks duplicated (as PBI and tasks) - Added by Carlos Jiménez about 8 years ago
Hi Emilio,
Thanks a lot.
RE: Sprint Board showing tasks duplicated (as PBI and tasks) - Added by Jose Angel Quintanar Morales over 7 years ago
Could you give me more details on how to solve this problem, I can not find the option you mention
RE: Sprint Board showing tasks duplicated (as PBI and tasks) - Added by Jose Angel Quintanar Morales over 7 years ago
Jose Angel Quintanar Morales escribió:
Could you give me more details on how to solve this problem, I can not find the option you mention
my version is 0.16.2