Project

General

Profile

Problem since migration from 0.7.0 to 0.10.0

Added by Emmanuel Despont almost 9 years ago

Hello everybody,
We've juste migrated the plugin to 0.10.0 version (We are in RM 2.5.2.stable)

And we are note able too use the plugin, thare are no item in the backlog (They were before) and in the sprints...
I checked autorization everything seems fine.

I should be able to see 1 backlog item...

Can anyone help me ?

Thanks in advance.
Emmanuel


Replies (2)

RE: Problem since migration from 0.7.0 to 0.10.0 - Added by Emmanuel Despont almost 9 years ago

I tried to delete the sprint 1 because it had no item. And I couldn't. That proof there are items.

I don't see hat is wrong with me.

Moreover to help I post my scrum configutation.:


I didn't changed any value for the new values because à bon't really understand their usage and I supposed that these values are pertinent.

Sorry for this poor English.
Emmanuel

RE: Problem since migration from 0.7.0 to 0.10.0 - Added by Emilio González Montaña over 8 years ago

It seems there are issues under the Sprint, but these issues tracker is not the PBI tracker (in you configuration tasks are Anomalie & Etude trackers).

Go to issues (Demandes) tab and select all the issues (any state, any tracker) with the Sprint 1, the selection will be not empty, edit them changing Sprint field to empty value.

    (1-2/2)